With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .
A
complete because the contractor meets the terms and conditions of the contract
B
incomplete because the buyer is not pleased
C
complete because the contractor is satisfied
D
incomplete because the specs are incorrect